Remodel Update Week 4
The destruction in the yard slowed in week four and the destruction in the basement accelerated. Outside we got our new egress window wells poured and the dirt around them is mostly filled back in. The foundation for the new mudroom is in place as well. The yard is still a muddy, rutted mess but at least we don’t have six-foot deep holes that people can fall in. I also can now take the lawnmower from the garage to the front of the house without walking through the alley and around the block on the sidewalk. It’s the little things!
The basement is a disaster zone however. The stairs got cut off half way down. I put a ladder at the end so I could get down and take pictures. The half of the floor being lowered has been broken up, hauled out and the dirt dug down. The half that isn’t being lowered has been cut out for the drain tile installation around the basement wall. The plumbers were here for two days rerouting plumbing to accommodate the various changes.
Next week framing starts and the new floor in the basement gets poured. I’m thinking this is maybe the ugliest it will look. 😀